NTDC defeats Iranian company in lawsuit

By Staff Reporter
Sunday – April 26, 2020
LAHORE: In what is a significant international victory, the national transmission and despatch company (NTDC), a company falling under the ministry of energy (MoE) power division, has prevailed in an international commercial arbitration initiated by an Iranian company - GAM ARAK Ind. Co. - in 2017 against the NTDC before an arbitral tribunal constituted under the rules of the international chamber of commerce (ICC), Paris.

According to an official statement, on Saturday, the spokesmen said that in its detailed award released on April 24, 2020, the arbitral tribunal has dismissed all the claims brought by the Iranian company and accepted and granted several counterclaims of NTDC amounting to approximately Rs 714 Million (approximately 71 crore or $4.5 million) plus interest at the rate of 7.925 percent per year as of the date of NTDC’s counterclaims dates back to July 2018 until complete payment.

While dilating upon the details, the spokesman said that the dispute arose out of a contract between the Iranian company and the NTDC executed in February 2011 for the design, supply, installation, testing, and commissioning of 500 kilo volt (kV) Guddu-Multan third circuit at Rahim Yar Khan 500 kV substation.

NTDC had terminated the contract due to “persistent delays” on the part of the Iranian contractor and the project was eventually completed by another contractor.

The spokesman said that the Iranian company, GAM ARAK initiated the arbitration in early 2017 claiming an amount of approximately Rs 180 million (approximately $1.1 million) on account of unpaid invoices and damages.

NTDC, apart from defending the claims, had filed its own counterclaims alleging the Iranian company’s delays, the costs required to complete the project from another contractor, and claims related to liquidated damages, mobilisation advances, customs duties, and demurrage.

On NTDC’s counterclaims, the arbitral tribunal held that NTDC had validly terminated the contract as the Iranian company was responsible for the delay in the project.

Accordingly, NTDC was awarded liquidated damages in the amount of JPY 93,591,449 and Rs 57,493,057 to compensate NTDC for the delay in project completion.

Furthermore, NTDC was also awarded the amounts of JPY 151,699,145 and Rs 167,546,831 as differential costs in respect of the new contractor engaged by NTDC to complete the project.

The tribunal also ordered the Iranian company to repay NTDC the unadjusted portion of the mobilisation advance given to it at the time of the project commencement amounting to JPY 49,830,686 and Rs 12,212,346 and a portion (Rs 28,133,604) of the demurrage charges paid by NTDC when shipments were stuck at port.

The spokesman further said that NTDC is also entitled to interest at the rate of 7.925 percent per annum for the Pakistani Rupee portion of the damages awarded in its favour.

The interest will accrue from July 6, 2018, and run until such time as payment of the award is made. Given NTDC’s near-total success on its counterclaims, the sole arbitrator also awarded NTDC 78 percent of its legal and other costs in the arbitration.

During the hearing, NTDC was represented in this matter by managing director Zafar Abbas, chief legal officer Hamza Randhawa and manager legal Arslan Akhtar.

NTDC had engaged the services of Pakistani law firm, Axis Law Chambers led by partner, Syed Shahab Qutub and assisted by Sameer Khosa, Maria Farooq, Abdullah Tariq, Hira Jaleel, Salman Ijaz, and Yumna Baloch.

NTDC did not engage any foreign lawyer or experts for this arbitration.

It is pertinent to mention here that in the context of international arbitrations where the success rate of Pakistan is extremely low, this award constitutes as a welcome victory at the international stage for the government of Pakistan (GoP), the NTDC statement concluded.